Insulated Concrete Homes - From the Ground Up


Overlooking Lake Oroville, CA

 
Work Day 9-Perimeter forms complete, rough plumbing installed, slab prepared and ready for rebar.  Foundation and slab was prepared as a mat slab to save on labor, material and time.  
 
  Work Day 9-Perimeter forms complete, rough plumbing installed, slab prepared and ready for rebar.  Foundation and slab was prepared as a mat slab to save on labor, material and time.  
Work Day 12-Slab was poured and finished with a hard trowel finish in about 6 hours.  Vertical rebar has also been installed to reinforce the walls.